沼气发酵微生物是人工生产沼气的重要因素。沼气微生物数量众多,可以获得各种微生物的基本生长条件,因此沼气发酵原料可以在微生物的作用下转化为沼气。大型沼气工程的启动和调试是指沼气池中厌氧活性污泥的过程从接种物和原料开始,经过驯化和培养,逐渐增加沼气池中厌氧活性污泥的数量和活性,直至沼气池运行达到要求的过程。
Biogas fermentation microorganism is an important factor in the artificial production of biogas. There are a large number of biogas microorganisms, which can obtain the basic growth conditions of various microorganisms. Therefore, biogas fermentation raw materials can be transformed into biogas under the action of microorganisms. The start-up and commissioning of large-scale biogas project refers to the process of anaerobic activated sludge in biogas digester, starting from inoculum and raw materials, through domestication and cultivation, gradually increasing the amount and activity of anaerobic activated sludge in biogas digester until the operation of biogas digester meets the requirements.
关于大型沼气工程的启动调试应在工程竣工验收合格后进行,同时还应做好下列的运行管理的基本要求:
The start-up and commissioning of large-scale biogas project shall be carried out after the project is completed and accepted. Meanwhile, the following basic requirements for operation and management shall be well done:
1、运行管理人员要熟悉大型沼气工程工艺、设施设备的运行要求和技术指标;
1. The operation and management personnel must be familiar with the operation requirements and technical indicators of large-scale biogas engineering process, facilities and equipment;
2、操作人员要熟悉该位置设施设备的操作要求和技术指标,并了解沼气工程工艺流程;
2. Operators must be familiar with the operation requirements and technical indicators of the facilities and equipment at the location, and understand the process flow of biogas engineering;
3、操作人员应准时准确填写操作记录,运营管理人员应定期检查原始记录;
3. The operators should fill in the operation records timely and accurately, and the operation management personnel should regularly check the original records;
4、运行管理人员和操作人员应按照工艺和管理规定检查结构、设备、电器和仪表的操作。
4. Operation management personnel and operators shall check the operation of structure, equipment, electrical appliances and instruments according to process and management regulations.
大型沼气工程管理要点:
Management points of large-scale biogas project:
1、投料量和周期应按工艺设计参数进行,并在实践中摸索出参数;
1. The feeding quantity and cycle should be carried out according to the process design parameters, and the excellent parameters can be found out in practice;
2、维持相对稳定的厌氧消化温度;
2. Maintain relatively stable anaerobic digestion temperature;
3、厌氧消化器的搅拌根据工艺要求进行。采用沼气搅拌的,在启动期间或产气量不足时,应辅以机械或泵等其它方式搅拌;
3. The mixing of anaerobic digester is carried out according to the process requirements. If biogas is used for mixing, machinery or pump should be supplemented during start-up or when gas production is insufficient;
4、厌氧消化器的搅拌不得与排泥同时进行;
4. The mixing of anaerobic digester should not be carried out simultaneously with sludge discharge;
5、宜每日监测:pH值、挥发酸、总碱度、温度、气压、产气量和沼气成分等指标,掌握厌氧消化池运行工况,并根据监测数据及时调整大型沼气工程运行方案或采取相应措施。
5. Daily monitoring: pH value, volatile acid, total alkalinity, temperature, air pressure, biogas composition and other indicators should be monitored daily to master the operation conditions of anaerobic digestion tank, and timely adjust the operation scheme of large-scale biogas project or take corresponding measures according to the monitoring data.
The above is about how to carry out the operation and management of large-scale biogas project. I hope it will help you. If you want to know more, please consult the biological desulfurization https://www.hneee.net Official website.